Carefully disbursing transportation funds day by day.

Vietnam.vn EN
25/11/2026 03:26:00

Focus all efforts on the race.

More than half of November has passed, and Mr. Le Thang, Director of Project Management Board 2, still maintains the habit of arriving at the office early in the morning to approve documents, ensuring that the disbursement of funds for the project is not disrupted.

Carefully disbursing transportation funds day by day - Photo 1.

The contractor is constructing the Cao Thanh bridge - one of the bridge projects with the most complex construction terrain on the Cho Moi - Bac Kan expressway. Photo: Ta Hai.

According to Mr. Thang's calculations up to November 17th, Project Management Board 2 has disbursed approximately 75% of the total allocated capital (around 3,979 billion VND). This figure is expected to increase to nearly 84% by the end of November.