According to a report by the Ministry of Construction , the operational plan from December 24th proposed by ACV has the advantage of bringing the facility into use sooner, gradually maximizing investment efficiency, and facilitating the implementation of the aviation transformation roadmap.
However, given that some items in component project 3 still have a large volume of work remaining, and the completion, acceptance of works, integration testing, and trial operation of essential systems are being implemented intensively in the final period of the year, the operational milestone needs to be considered based on actual results.