Airlines are increasing flights to Long Thanh to meet the peak Tet holiday season.
According to the initial operational plan announced by the Vietnam Airports Corporation (ACV), Long Thanh International Airport will officially open for commercial flights from 0:00 on December 24th. The airport's operational plan is divided into three phases with increasing scale. Phase 1 runs from December 24th, 2026 to the end of March 2027, coinciding with the 2026-2027 winter flight schedule and encompassing the entire peak period of the New Year and Lunar New Year (Year of the Goat 2027). The next two phases will be implemented from April to October 2027 (2027 summer flight schedule) and from October 2027 onwards.
Long Thanh Airport has completed the lighting test on the roof of the terminal building.
Photo: Ly Quang Vien
In the initial phase starting in late December, ACV plans to operate a maximum of approximately 366 flights per week at Long Thanh Airport, including 322 domestic and 44 international flights, equivalent to an average of about 20-30 flights per day. However, during the peak period serving the 2027 Lunar New Year, the number of flights at Long Thanh is expected to increase to 30-40 flights per day to directly alleviate pressure on Tan Son Nhat Airport, which is currently operating beyond its designed capacity.
Notably, the direct trunk route connecting to Hanoi will be the "opening flight" for Long Thanh on its first day of commercial operation. The registration plan shows that both of the country's largest airlines, Vietnam Airlines and Vietjet Air, will operate flights on the Long Thanh - Hanoi route starting from December 24th.